What’s on the Earned Value poster
The rule, 3 worked examples, and the mistake everyone makes.
- Earned value measures work actually completed against both the money spent and the pl…
- CV = EV − AC · SV = EV − PV · CPI = EV/AC
- PV 100, EV 80, AC 90 = Late and overspent
- CPI = 0.9 = Costing more than planned
- SPI = 1.1 = Ahead of programme
- Common mistake: Reading spend as progress → Measure the work completed
Educational reference. Earned value needs a baseline and honest measurement, both governed by the project's controls.
Questions about the Earned Value poster
- What’s on the Earned Value poster?
- The rule, 3 worked examples, and the mistake everyone makes. Earned value measures work actually completed against both the money spent and the pl…; CV = EV − AC · SV = EV − PV · CPI = EV/AC; PV 100, EV 80, AC 90 = Late and overspent; CPI = 0.9 = Costing more than planned; SPI = 1.1 = Ahead of programme; Common mistake: Reading spend as progress → Measure the work completed. Educational reference. Earned value needs a baseline and honest measurement, both governed by the project's controls.
- Who is the Earned Value poster for?
- Earned Value belongs to the Civil Engineering section rather than to a school year, because engineering is not something one grade owns. Anyone learning construction management can pin it up — a beginner, a student mid-course, or someone revising years later.
- When should you use the Earned Value poster?
- Reporting progress on a project where spend and progress have parted company. A wall chart earns its place by being glanceable from where the work is happening, so Earned Value belongs on the wall where that engineering work actually happens, within glancing distance, rather than filed away.
- What other posters go with Earned Value?
- Cost Estimating, Critical Path Method and Float & Slack sit alongside Earned Value in the Civil Engineering section. Printed together they make a wall rather than a single sheet, which is how a reference set actually gets used.Cost EstimatingCritical Path MethodFloat & Slack
- Is the Earned Value poster free to download and print?
- Yes. Earned Value downloads as a free PDF with no account, no email and no watermark, like everything else in the Civil Engineering section. Print as many copies as you like for a home, a classroom, a library or a tutoring group; reselling the file is the only thing the licence rules out.Read the licence
- What size does the Earned Value poster print at?
- Earned Value is a vector PDF laid out for US Letter, and prints on A4 with Fit to page — the same file, no separate download. Because every mark on it is drawn rather than photographed, it stays sharp enlarged to A3, A2 or A1 at a copy shop. Colour carries emphasis only, so a greyscale print of Earned Value loses nothing.Printing guide
Related posters
Charts that sit alongside Earned Value on the same wall.
Browse every Civil Engineering poster, or start from the full catalogue.